SHY長軸液下泵安裝及調(diào)試
2012-09-04
SHY長軸液下泵安裝及調(diào)試
安裝:
泵組裝好后,盤動聯(lián)軸器,看是否轉(zhuǎn)動靈活,檢查有無金屬摩擦聲
檢查泵軸和電機軸的同心度,兩聯(lián)軸器外面上的差數(shù)不得超過0.3mm
軸襯需能浸在液體中,否則應(yīng)自出口管路中引出(或從外部接入)適量液體,潤滑軸襯,防止干磨損壞。
在化工流程系統(tǒng)中,若有雜物落入容器時,為防止雜物損壞泵體,可在吸入管外,裝上所需形式的攔污網(wǎng)。
泵的吸入口到容器底部之距離為吸入口徑的1.5~2倍,四周不應(yīng)少于2.5倍,小口徑取大值,大口徑取小值。
泵之出液管路應(yīng)加設(shè)支架支撐,其重量不允許加在泵出口法蘭上。
安裝完畢后,還需檢查各螺帽是否旋緊,并應(yīng)盤動聯(lián)軸器,轉(zhuǎn)動靈活后方可將泵和電機組裝在容器上,裝好后再檢查一次。
After installing the pump, check whather the coupling runs flexibly and check whether there are some metal friction sounds.
Check the concentricity of the pimp shaft and motor shaft, The difference on the outer round of the two couplings can't exceed 0.3mm
The bearing bush should soak into the liquid, Otherwise you should lead to appropiate liquid from the self-outlet pipeline (or joint form the outside),lubricate bearing bush and prevent the dry mill damaging.
In chemical process system, if there are some odds to drop into the container, in order to prevent the odds from damaging the pump body, you can install a proper conservancy trash-rack at the suck pipe place.
The distance from the pump suck entrance to the bottom of the container is 1.5~2times of the suck bore. Four rounds can't be less 2.5times. The small bore gets the large value and large bore get the small value
The liquid-out pipeline of the pump should separately set up the support frame and its weight can't be allowed to add the pump oytlet flange.
After finishing installation. Check whether the nuts of all the parts are tightened and then install the pump and motor on the container after the coupling runs flexibly. After installtiong, check it again.
起動與停車
檢查軸承腔,使之保持有定量干凈的黃油。通常以充滿空腔容積的1/2~1/3為宜。避免運轉(zhuǎn)時軸承溫升過高。
盤動聯(lián)軸器、檢查有否輕重不均勻。否則需找出原因,待消除后再運轉(zhuǎn)。
若采用外部沖洗潤滑軸襯,在起動電機前需將外部液體通入軸襯中。
檢查電機的轉(zhuǎn)向,使之與泵的規(guī)定旋轉(zhuǎn)方向相同
關(guān)閉出口管路中的閘閥及壓力表。
起動電機后打開壓力表,慢慢的打開出口管路閘閥到所需位置,投入正常運轉(zhuǎn)。
正常停車,應(yīng)先慢慢關(guān)閉出口閘閥,然后停止電動機,關(guān)閉壓力表。
長期停車或長期不用,應(yīng)將泵從容器中取出,清晰、重裝、加油保管。
check the bearing cavity and let it keep a ration clean butter. Usually it's appropriate to fill with the empty cavity capacity 1/2~1/3, avoid the bearing temperature rising while runing.
Check whether the coupling is even on weight, otherwise you should find out the reason and get rid of it and then run it.
If adopting the exterior washing lubricating bearing bush, before starting the motor, lead the exterior liquid to wash the bearing bush
Check the motor running direction and let it same as the ruled rotary direction of pump.
Close the gate valve and pressure meter on the outlet pipeline.
First start the motor and then open the pressure meter, slowly open the gate valve on the outlet pipeline to the desired position and then put into the normal running.
運轉(zhuǎn)
軸承溫度不得高于80℃,軸承盒內(nèi)應(yīng)有適量的黃油。
隨時注意保證黃油的潔凈
泵運轉(zhuǎn)過程中發(fā)生下列故障,應(yīng)立即停車,并進行檢修。
The bearing temperature can't be high 80℃ and there should be appropriate butter in bearing box.
Keep and guarantee the butter pure and clean at any time .
上海帕特泵業(yè)制造有限公司
2012年09月04日 星期二
上海帕特泵業(yè)制造有限公司相關(guān)系列產(chǎn)品如下,更多詳細內(nèi)容可以點擊產(chǎn)品中心查詢
1、EG系列離心泵 2、PTL系列單級單吸離心泵 3、SLB系列單級雙吸泵 4、THY系列長軸液下泵
5、UHB-ZK系列氟塑料砂漿泵 6、IH系列標準化工泵 7、IHF系列氟塑料離心泵 8、QBK系列氣動隔膜泵
9、ZX系列自吸泵 10、G型單螺桿泵 11、ZB3A型不銹鋼轉(zhuǎn)子泵 12、ZW系列自吸式排污泵
13、YW系列液下式排污泵 14、WQ系列潛水排污泵 15、ED臥式多級離心泵 16、CDL系列輕型立式多級泵
17、JWM機械隔膜計量泵 18、JYMZ液壓隔膜計量泵 19、J-W系列柱塞式計量泵 20、J-X系列柱塞式計量泵
21、QJ系列深井潛水泵 22、CQ系列磁力泵 23、ZCQ系列自吸磁力泵 24、CQB-F系列氟塑料磁力泵
25、2X系列旋片式真空泵 26、2BV系列水環(huán)式真空泵 27、2XZ系列真空泵 28、SK系列水環(huán)真空泵
關(guān)于 液下泵 的新聞上海帕特泵業(yè) |
移動端快速訪問 |